Germany's capacity mechanism: Gas plants must be h2-ready
State aid approval was the final formality standing between Germany and its first capacity tender. The scheme rests on the Electricity Security of Supply and New Capacity Act (StromVKG), designed to secure enough capacity for power generation, storage and flexible demand. The federal government can commit between €15.6 billion and €35.2 billion to the programme.
Federal Economics and Energy Minister Katherina Reiche called the approval the missing piece for greater planning and investment certainty. She expects the law to deliver a more reliable and, over time, more affordable power supply.
First round puts 9 gigawatts on the table
The capacity market takes full effect in 2031 and is being built up through staged tenders. The opening round covers roughly 9 GW of long-term capacity, translating to around 10 GW of plant capacity depending on the technology. Contracts go to plants that can deliver power continuously over extended periods, covering the country through prolonged low-wind, low-sun spells.
The Bundesnetzagentur ran the first tender on September 8, with a second round set for December 29. Any technology can compete, provided it delivers reliable, dispatchable capacity and supports security of supply.
New gas plants must be hydrogen-ready
A further 2 GW without a long-term requirement goes to tender in May 2027, followed by additional rounds in 2027 and 2029 covering power plants, storage, flexible demand and existing assets. Contracts run for up to 15 years, and every capacity under contract has to operate climate-neutral by 2045 at the latest. Any new gas plant securing a long-term contract must also be built hydrogen-ready.
The Bundesnetzagentur sets each tender volume against current European and national security-of-supply monitoring to ensure the full 2031 capacity requirement is met. A comprehensive capacity market is planned to cover needs from 2032 onward, with the underlying rules due in 2027.
Separate funding track for hydrogen conversion
Alongside the capacity mechanism, Germany is preparing decarbonisation tenders to support converting existing gas plants to hydrogen. Tenders for 2 GW of capacity, to be converted from gas to hydrogen by 2040, are due to launch before the end of 2027. A further 2 GW follows between 2032 and 2035, with conversion completed by 2043. This funding track sits outside the current state aid approval and will be regulated separately.
(Source: Federal Ministry for Economic Affairs and Energy/ 2026)